Several upgrade and rehabilitation projects are currently underway along the N4 as part of TRAC’s ongoing  commitment to maintaining a safe and reliable corridor. While construction activities will pause from 01  April to 07 April 2026, all road construction zones will remain active and traffic-control measures will stay  in place in line with road safety requirements.  

With multiple projects at various stages of completion along the route, motorists may still encounter traffic  accommodation in certain areas and are encouraged to plan ahead and allow additional travel time where  necessary. To assist road users in planning their journeys, TRAC has provided an overview of the major  projects currently underway along the N4, together with their progress to date.

Section 

Project 

Start 

Completion 

Progress 

Traffic  

Impact

Contractor

Solomon  

Mahlangu Dr – 

Bronkhorstspruit N4-1 km 21 – 25  / N4-2 km 0 – 30

Rehab 

Oct  

2025

Sep 2027 

25% 

Shoulder  

& lane  

closures

TauPele  

Construction

Van Dijksdrift IC  – Wonderfontein N4-4 km 9 – 47 /  N4-5 km 0 – 10

Rehab 

Sep  

2025

Mar 2027 

20% 

Shoulder  

& lane  

closures

Actophambili  Construction

Schoemanskloof N4-6Y km 2.7 – 62

Rehab & 

New  

passing  

lanes

Oct  

2024

Oct 2027 

42% 

Shoulder  

& lane  

closures  

Stop/Go

TauPele  

Construction

Montrose – 

Alkmaar 

N4-7X km 23.09  – 32.72

Rehab & 

New paved  shoulders

Mar  

2026

Jun 2027 

1% 

Shoulder  

& lane  

closures

TauPele  

Construction

Press Release 

Crocodile Gorge N4-7 km 74.1 – 

90.05

Upgrade & 

Rehab

Mar  

2025

Feb 2028 

35% 

Stop/Go’s as needed

Raubex  

Construction

Malalane – 

Hectorspruit 

N4-8X km 23 – 39

Rehab & 

New  

passing  

lanes

Feb  

2026

Aug 2027 

0% 

Lane  

closures  

&  

Stop/Go’s

Roadspan

Hectorspruit – 

Lebombo Border N4-8X km 39 – 70

Rehab & 

New  

passing  

lanes

May  

2025

May 2027 

26% 

Lane  

closures  

&  

Stop/Go’s

Roadspan /  WBHO JV

Ressano Garcia – Moamba  

EN4-1 km 0 – 

41.29

Rehab & 

New  

passing  

lanes

Oct  

2024

Jan 2028 

27% 

Stop/Go’s 

WBHO  

Projects  

Mozambique

Moamba IC – 

Tchumene IC 

EN4-2 km 0 – 25

Rehab 

Jun  

2025

Jul 2026 

14% 

Daytime  

Stop/Go’s

TC Projectos  LDA

Increased traffic volumes 

Traffic volumes are also expected to increase drastically over the Easter weekend. To accommodate this,  all TRAC N4 toll plazas will be fully staffed during identified peak dates: 

  • 27 March  
  • 02 April 
  • 03 April 
  • 06 April  
  • 07 April  

Road users are also reminded that all existing payment methods remain available at all TRAC toll plazas  along the N4. These are: 

  • Tag 
  • Tap & Go 
  • Fleet cards 
  • Garage/petrol cards 
  • Cash 

24-hour free roadside assistance 

TRACAssist – TRAC’s free, 24-hour roadside emergency service – will increase patrols across the route  during the Easter period. In partnership with the TRAC Helpdesk, the teams will respond rapidly to  incidents, with additional units strategically stationed in high-traffic areas on peak travel days.

Press Release

Border crossing guidance 

As Easter travel builds along the N4 corridor, increased traffic volumes and peak-period delays may be  experienced at the Lebombo and Ressano Garcia border posts. TRAC reminds road users that while it  supports congestion relief near the border, all port of entry operations are managed by government  authorities.  

To support traffic flow, the Easter Traffic Management Plan for the border posts will run from 27 March to  12 April 2026, with one-stop border processing at KM7 from 27 March to 04 April 2026. Key measures  include: 

  • A roadblock at the Coopersdal intersection; 
  • A control point at the entrance of KM7 where all vehicles will be classified: 

o Light vehicles (Class 1) en route to the border will proceed directly; 

o Loaded light delivery vehicles (bakkies) and taxis will be diverted through the Komatipoort Load  Control Centre and processed at KM7 before being escorted to the border; 

o Trucks will continue to utilise the KM7 staging area, with dedicated lanes for vehicles  transporting perishable goods; 

In the event of a blockage on the N4 in South Africa the following measures will take effect: o Eastbound local traffic will use Tenbosch Road to reach Komatipoort; 

o Westbound local traffic will use Strydomblock and Coopersdal to reach Malalane. 

Pedestrian processing will take place at the pedestrian processing office, with South African and  Mozambican officials co-locating from 27 March to 04 April 2026. Additional processing areas have been  identified to help manage increased volumes and reduce queues. 

Practice road safety  

TRAC CEO, Alex van Niekerk, urges travellers to prioritise road safety and make use of TRAC’s 24-hour  Helpdesk for assistance or route-related information. “Easter is a time when families travel long distances  to spend time together, and road safety must remain everyone’s top priority,” says Mr Van Niekerk.  

“TRAC is committed to keeping the N4 safe and operational, but every driver plays a part. Plan your trip  properly, avoid drinking and driving, take breaks if you feel tired, and respect the rules of the road. If we all  do our part, we can make this Easter a safer one for everyone.” 

Roadside assistance and real-time route information 

TRAC further encourages road users to plan their journeys carefully and, where possible, travel during  daylight and busier periods to reduce risks such as road spiking or other criminal activities. Travellers are  also reminded to reach out to the TRAC Helpdesk that manages TRAC’s free 24-hour roadside assistance  units, TRACAssist, in the event of any incident or emergency along the Maputo Corridor. 

Press Release

Toll Free TRAC 24-hour Helpdesk contact numbers: 

  • South Africa: 0800 87 22 64 / +27 82 881 4444 
  • Mozambique: 800 9022 

For real-time traffic updates on the TRAC N4, follow: 

  • X: @TRACN4Route 
  • WhatsApp Channel: https://www.whatsapp.com/channel/0029VaeDDXP7YSdCacuH3n1V 

Share this article:

Leave a Reply

Your email address will not be published. Required fields are marked *

most popular

what you need to know

in your inbox every morning